Also known as AND-Join.

Contents

Characteristics

  • several parallel streams of work convergent to one activity
  • the activity after the synchronization waits for the completion of all paths before starting
  • no merging activity must be started, untill all incoming streams have completed
  • merging of Parallel Split paths

BPMN

Synchronization.png

  • revise Content only could be startet, if both incoming activities are finished
  • revise Content waits for the complete finished incoming activities
  • a AND-Gateway must not be omitted like in a Multiple Merge

jPDL

Synchronization-jPDL.PNG

  • Synchronization with a Join Node